Manchester Piccadilly has now officially reopened after a nine-day closure.
In case you hadn’t heard, Manchester Piccadilly train station closed on Saturday 14 February while a ‘once-in-a-generation upgrade’ was carried out – with very few train services running in or out of the station in the process, and as you’d expect, widespread disruption caused for those travelling around the region.
But thankfully now, after many journeys were impacted for those travelling to and from major destinations like Manchester Airport, and on the West Coast Mainline, the station is now back up and running.
The public are being thanked for their ‘patience’ while the the journey-improving work was carried out this past week.
Network Rail invested £7.9m into the major upgrade, with the main points of action being to improve tracks, points, and signalling systems on the southern approach to Manchester Piccadilly station.
ADVERTISEMENT
🎥VIDEO UPDATE🛤️
👷🏼♂️Teams are carrying out final inspections after a 9-day closure for £7.9m track upgrades at Piccadilly 🔧
🏗️Trains will run from 5am tomorrow🚆
‼️Follow up work is needed on Sun 1 and Sun 22 March – please check @nationalrailenq🙏
Teams worked to replace 11 sets of points, renew timber sleepers with modern, concrete equivalents, and also bring lineside equipment ‘bang up to date’ across six lines to improve future journeys for passengers and freight.
Investment in this apparent ‘critical stretch’ of track had been long awaited, as any issues with the ageing infrastructure could’ve disrupted all trains running in and out of Manchester.
ADVERTISEMENT
The closure also resulted in what was said to be one of the largest rail replacement bus operations the city has seen in recent memory, with a total of 8,922 services running over the course of the nine days to keep passengers on the move.
Manchester Piccadilly has now reopened to the public after its £7.9m upgrade / Credit: Network Rail
“We would like to say a big thank you to passengers for their patience while this once-in-a-generation upgrade has taken place over the last nine days,” commented Brian Paynter, who is the Capital Delivery track director at Network Rail.
“Manchester Piccadilly is one of the country’s busiest stations and it’s a key hub for people travelling to the North West.
“Upgrading the track over six lines in what’s known as the Piccadilly corridor will make journeys more reliable and the points and signalling systems less prone to faults – meaning fewer delays for passengers. It’s all part of our long-term commitment to invest millions of pounds to make the North West’s railway fit for the future.”
Unfortunately thought, the disruption doesn’t quite end there, as this coming Sunday 1 March, and then again on Sunday 22 March, routine follow-up work will take place to secure the new railway foundation stone through a process called tamping.
This will impact trains until passed midday, with passengers advised to check online ahead of time if planning travel on those dates.
Featured Image – Network Rail
News
Police provide update after stabbing of 14-year-old boy at Manchester Arndale carpark
Emily Sergeant
Police have provided an update following the stabbing of a young boy in Manchester city centre over the weekend.
At around 3:15pm this past Saturday afternoon (17 October 2026), officers from Greater Manchester Police (GMP) were called out to reports of a stabbing on the ninth floor of the Arndale carpark in Manchester city centre.
Emergency services attended the scene, and a 14-year-old boy was taken to hospital with injuries consistent with a stab wound.
Thankfully, the victim’s injuries are not believed to be life-threatening or life changing, but an investigation and enquiries are ongoing.
Detective Inspector Sam Jones, of GMP’s City of Manchester District CID, said this will ‘understandably’ cause concern, but has assured the public that police believe this to be an ‘isolated incident.
“Detectives at the scene are working extremely hard to process the scene with Crime Scene Investigators,” explained DI Jones in an update statement issued.
“The car park is expected to be closed for several hours, so we ask for your understanding and patience whilst we gather evidence to bring these offenders to justice.
“Detectives and Officers will be in the area today to speak with local businesses and members of the public to provide reassurance. This is believed to be an isolated incident with no risk to the wider public.
“Greater Manchester Police are committed to diligently investigating all knife crime and bringing offenders to justice, and we are asking for anyone with information about this incident to come forward to assist with our enquiries.”
Anyone with information is asked to contact police on 101, quoting log 2050 of 17/10/2026, or via the LiveChat function. Alternatively, contact Crimestoppers anonymously on 0800 555 111.
Featured Image – Wikimedia Commons
News
TfGM issues statement as ‘essential’ work begins on three major Metrolink lines across Greater Manchester
Emily Sergeant
Passengers are being urged to plan ahead as no trams will be running on three major Greater Manchester lines for the next two weeks.
If you need bringing up to speed a little, as part of the ongoing £150m investment into Greater Manchester’s tram network, essential improvement work is being carried out on three major Metrolink lines across the region in a bid to make the network ‘safer’ and ‘more resilient and reliable for passengers’ for years to come.
This means that from today (Monday 19 October) through to Sunday 1 November, tram improvement works will take place at Deansgate-Castlefield, and Trafford Bar.
Additional works will also take place in the city centre during this time, allowing TfGM to keep closures of the tram network to a minimum.
During the dates above, no trams will run on the Altrincham, Trafford Centre, and Eccles lines.
A number of shuttle bus services will the running over the course of the two-week closure, however – with services arriving every 10 or 15 minutes, depending on the line, and you can find a full list of these here.
But despite the alternative services, widespread disruption is still expected for hundreds of people.
TfGM has issued a statement on the works being carried out, and offered support to anyone who may need it: “This is essential work that will help keep our tram network safe, reliable and fit for the future. We’re sorry for the disruption and we’ll be doing everything we can to make sure people can still get around while it’s taking place.
“We’ve listened carefully to feedback from customers during previous closures and have introduced more direct shuttle buses between key locations and extra buses on local Bee Network routes.
“If you use any of the affected lines, now is the time to check your travel plans.
“We’d encourage everyone to visit the Bee Network website or app before travelling so they can see the options available to them and allow extra time where necessary.”
Services will resume on these lines from start of service on Monday 2 November.
However there will be some minor route changes through the city centre in place from Monday 2 to Wednesday 4 November, so it’s important to check your journey before you travel.